Work at MVVA Inc.
St Louis Arch Grounds Renovation
As MVVA Project Manager I carried the role of a pivotal connector almost 8 years for the local Gateway Arch Park Foundation, NPS, MVVA design team, subconsultants, and contractors.
Waterfront Toronto Port Lands - New Don River Mouth Earthwork
As MVVA Senior Associate staff tasked to manage the client and civil engineers design and documentation of the excavation and management of site soils, groundwater management, and construction sequence of new subgrade for the new Don River. The quantities of soils material were significant- about a million cubic meters of soil excavated and managed, and thousands of secant pier walls to bedrock to retain groundwater outside the entire river mouth area.